Selected MCQ

Current Question
If 6 men can do a work in 12 days, how many days will 4 men take?
  • A. 16
  • B. 18
  • C. 20
  • D. 24
Correct Answer: B
Explanation:
Work = 72 ⇒ 72/4 = 18 days.
Related Question 1
If 9 workers can complete a job in 6 days, how many days will 3 workers take?
  • A. 12
  • B. 15
  • C. 18
  • D. 20
Correct Answer: C
Explanation:
Work = 54 ⇒ 54/3 = 18.
Related Question 2
If 12 men can complete a work in 10 days, how many days will 15 men take?
  • A. 6
  • B. 8
  • C. 10
  • D. 12
Correct Answer: B
Explanation:
Work = constant ⇒ 12×10 = 15×x ⇒ x = 8.
Related Question 3
A, B, and C can complete work in 8, 14, and 16 days. How many days will A alone take?
  • A. 13
  • B. 11
  • C. 12
  • D. 15
Correct Answer: A
Explanation:
Derived from partial work relation.
Related Question 4
Four men and two women can complete the work in 2 days. If two men alone take 5 days, how many days will four women take to complete the work ____.
  • A. 15 days
  • B. 10 days
  • C. 8 days
  • D. 20 days
Correct Answer: B
Explanation:
Use work equations: 4M+2W = work/2 and 2M = work/5 → solve for W.
Related Question 5
12 children take 16 days to finish work. Time for the same work with a different number is ____.
  • A. 3 days
  • B. 4 days
  • C. 6 days
  • D. 8 days
Correct Answer: C
Explanation:
Work is inversely proportional.